Construction Updates
Construction Update August 2023
2023-08-10
Construction during July and to start August as been progressing well. Our development team has provided the below update on construction progress:
- Internal drainage is now complete
- Following completion of the road subgrade, water mains installation is now underway.
- Drainage outfall work through the Hume Freeway corridor is nearing completion.
- Barry Road roundabout works pushed back to commence in Mid-August
![](https://marranrun.com.au/wp-content/uploads/2023/10/Site-2-scaled-1.jpg)